Area of Interest 5
āPreliminary Alternative 5.1
-
New storm drain in the S Briar corridor extending to 24th St/Broadway Rd intersection
-
Increase storage capacity in the storage basin at Robson Elementary School fields (requires agency partnership agreement)
-
Connect Robson Elementary School basin to existing storm drain system in Gilbert Rd corridor
Preliminary Alternative 5.2
-
New storm drain system in 24th St corridor from Broadway Rd to Pueblo Ave
-
Potential new underground storage facility under existing church parking lot at northwest corner of 24th St/Pueblo Ave (requires agency/organization partnership agreement)
Preliminary Alternative 5.3
-
New storm drain system in 24th St corridor and S Briar corridor from Broadway Rd to Silvergate Park
-
Expand storm water storage capacity at Silvergate Park
Area of Interest (AOI) 5 is located along 24th Street and Broadway Road.
Stop or move at your speed by using the slider